Construction Schedule
Day 1- Friday Oct 22nd (Door Knock Day)
A C T I V I T Y
Start Time
Finish Time
Duration
Plans Stamped, All Permits Pulled
DONE
N/A
Builders meet crew at Crowne Plaza
6:45 AM
7:30 AM
AMBUSH OFFSITE
10:00 AM
2:00 PM
4 HR
Braveheart Ambush Check-in * subject to change
10:00 AM
11:00 AM
1 HR
BRAVEHEART AMBUSH * TBD
11:00AM
1:00 PM
2 HR
Staging Set up
11:00 AM
On going
N/A
Check-in Set up
11:00 AM
On going
N/A
Deliver Storage Bins
11:00 AM
11:30 AM
.5 HR
Deliver Framing package to staging
12:00 PM
1:30 PM
1.5 HR
Deliver United Rentals Equipment
12:00 PM
1:30 PM
1.5 HR
Mark power lines, underground utilites
12:00 PM
1:00 PM
1 HR
Deliver Demo/Excavation Equipment
12:00 PM
1:00 PM
1 HR
Site Meeting- All PROJECT MANAGERS
1:00 PM
2:00 PM
1 HR
Builder Walkie Set up
2:30 PM
3:30 PM
1 HR
Deliver Dumpsters
4:00 PM
5:00 PM
1 HR
Salvage wood from ex. Chicken/rabbit pen
4:00PM
5:00 PM
2 HR
Remove & Relocate mulch
4:00PM
5:00 PM
1.0 HR
Remove & Relocate firewood
4:00PM
5:00 PM
1 HR
Remove ex. Fencing
4:00PM
5:00 PM
1 HR
Begin installation of tree house supports
4:00PM
12:00 AM
8 HR
Surveyor layout - House, Garage
4:30 PM
6:30 PM
2 HR
Stage light towers around site
5:00 PM
6:00 PM
1 HR
Deliver Builders RV's
5:00 PM
6:00 PM
1 HR
House Move out
5:00PM
7:00 PM
2 HR
Disconnect Utilities
6:00 PM
7:00 PM
1 HR
Tree Removal
6:00PM
8:00 PM
2 HR
Out Building Demo
8:00 PM
10:00 PM
2 HR
Drop gravel for new drive
8:00 PM
9:00 PM
1 HR
Site Drainage
8:00 PM
1:00 AM
5 HR
Cut New Drive/Circle drive
9:00PM
11:00 PM
2 HR
Locate, pump and abandon septic tank/pipe
10:00 PM
11:00 PM
1 HR
Excavate for retaining walls/ house slab & footer
10:00PM
3:00 AM
5 HR
Prep pad for new foundation- Main house
10:00PM
3:00 AM
5 HR
Prep pad for new foundation- Garage/Gym
10:00PM
3:00 AM
5 HR
Surveyor to pin slab/ set elevations
10:00 PM
3:00 AM
6 HR
Deliver gravel into Garage/Gym pad
11:00 PM
3:00 AM
4 HR
gravel delivery-Haulers
11:00 PM
3:00 AM
4 HR
Day 2- Saturday Oct 23rd
A C T I V I T Y
Start Time
Finish Time
Duration
Place footers/place rebar/form slab- Garage/Gym - Rigid Insulation
Midnight
7:00 AM
7 HR
Deliver gravel into Garage/Gym pad
1:00 AM
3:00 AM
.5 HR
Stage Pump trucks (2)
2:00 AM
3:00 AM
1 HR
Place and pour footers- Main house/porch/garage posts
3:00 AM
5:00 AM
2 HR
convey stone for retaining wall footer
3:00 AM
5:00 AM
2 HR
Slab Rough-in Plumber- Garage/Gym
3:30 AM
4:30 AM
1 HR
Footing/Foundation inspection- Garage/Gym
4:30 AM
5:00 AM
.5 HR
Set House Foundation Forms
5:00 AM
7:00 AM
2 HR
Pour/Finish Foundation- Garage/Gym footings/slab
5:00 AM
9:00 AM
4 HR
stage retaining wall material
6:00 AM
7:00 AM
1 HR
gravel delivery for crawl- con't
6:00 AM
7:00 AM
2 HR
Footing/Foundation inspection- Main House
6:30 AM
7:00 AM
.5 HR
convey gravel for crawlspace-con't
7:00 AM
8:00 AM
1 HR
Install retaining wall
7:00 AM
7:00 PM
12 HR
Trench electric underground/phone
7:00 AM
9:00 AM
2 HR
Install water, sewer, gas and elec to septic
7:00 AM
10:00 AM
3 HR
Pour House Foundation Forms
7:00 AM
9:00 AM
2 HR
All Concrete: cure time house/gym/garage
9:00 AM
3:00 PM
5 HR
Camera Demo/ Demo main house
9:00 AM
3:00 PM
6 HR
Set up Spider power boxes and run cable
3:00 PM
4:00 PM
1 HR
Stage Framing Materials- Garage/Gym
3:00 PM
4:00 PM
1 HR
Stage Framing Materials- House floor
3:00 PM
4:00 PM
1 HR
Stage Crane A - Steel Beam Delivery
3:00 PM
4:00 PM
1 HR
Strip forms- main house
3:00 PM
4:00 PM
1 HR
Rough in soil pipe below house/through foundation wall
3:00 PM
5:00 PM
2 HR
Snap out walls on slab- Garage/Gym
3:00 PM
4:00 PM
1 HR
Set posts/support for house tree feature
3:00 PM
4:00 PM
1 HR
waterproof foundation wall
3:00 PM
5:00 PM
2 HR
Set wall panels- Garage/Gym
4:00 PM
9:00 PM
5 HR
Set green plate, joists, and Advantech- House
4:00 PM
10:00PM
6 HR
Set deck/breezeway/garage porch posts
6:00PM
9:00 PM
3 HR
install septic field
7:00PM
Midnight
5 HR
Backfill/Top dress site
7:00 PM
9:00 PM
2 HR
Stage trusses- Garage/Gym
7:00PM
8:00 PM
1 HR
Set trusses/Sheathing- Garage/Gym
8:00PM
Midnight
4 HR
Stage Crane B
9:00PM
10:00 PM
1 HR
Snap out walls on deck- main house
9:00 PM
10:00 PM
1 HR
Stage wall panels- House
9:00 PM
10:00 PM
1 HR
Set First floor wall panels- main house
10:00PM
4:00 AM
6 HR
Day 3- Sunday Oct 24th
A C T I V I T Y
Start Time
Finish Time
Duration
Sheath Garage/Gym roof
Midnight
4:00 AM
4 HR
Roof Install- Garage/Gym
2:00 AM
2:00 PM
12 HR
Stage trusses-House
4:00 AM
5:00 AM
1 HR
Set Roof Trusses/Sheath roof- House
5:00 AM
Noon
7 HR
Begin deck install
5:00 AM
5:00PM
12 HR
Termite pretreat
6:00AM
8:00 AM
2 HR
Deliver Windows/Doors
6:00 AM
7:00 AM
1 HR
Hang Durock at chimney
7:00AM
9:00 AM
2 HR
Window/Door Install/ Interior Framing
7:00 AM
11:00 AM
4 HR
Stage interior tree feature
7:00 AM
8:00 AM
1 HR
Install interior tree feature
8:00 AM
10:00 AM
2 HR
Set log truss at front entry
10:00 AM
Noon
2 HR
Design Producer Electrical Walk-Through
11:00 AM
12:00 PM
1 HR
Design Producer Low Voltage Walk-Through
11:00 AM
12:00 PM
1 HR
Energystar compliance work
11:00 AM
7:00 PM
8 HR
Rough-in Plumber
11:00 AM
7:00 PM
8 HR
Rough HVAC Start
11:00 AM
7:00 PM
8 HR
Rough-In Electric
Noon
8:00 PM
8 HR
Stage stone veneer, sand and mixers
Noon
1:00 PM
1 HR
Pick up Framing/ Drywall nailers/ Deadwood/ Cornice
Noon
8:00 PM
8 HR
Stage siding materials
1:00 PM
2:00 PM
1 HR
Install CMU blocks for stone @ column bases
1:00 PM
7:00 PM
6 HR
Exterior stone veneer
2:00 PM
2:00 PM
24 HR
Siding Install
2:00 PM
2:00 AM
12 HR
Stage roofing materials
2:00 PM
3:00 PM
1 HR
Design Producer Blocking Walk-Through
2:00 PM
3:00 PM
1 HR
Rough Phone/ Cable & Internet/ Security
3:00 PM
8:00 PM
5 HR
Roof Install- House
3:00 PM
3:00 AM
12 HR
Install Fireplace
4:00 PM
7:00 PM
3 HR
Framing inspection
6:00 PM
7:00 PM
1 HR
Rough electrical Inspection
6:00 PM
9:00 PM
1 HR
HVAC Inspection
6:00 PM
9:00 PM
1 HR
Plumbing Inspection
6:00 PM
9:00 PM
1 HR
Measure for blinds
8:00 PM
10:00 PM
2 HR
Insulate Walls- Batts
8:00 PM
2:00 AM
6 HR
Day 4- Monday Oct 25th
A C T I V I T Y
Start Time
Finish Time
Duration
Insulation Inspection
1:00 AM
2:00 AM
1 HR
Energystar Inspection
1:00 AM
2:00 AM
1 HR
Clean site/house
2:00 AM
4:00 AM
2 HR
Permanent power
3:00 AM
6:00 AM
3 HR
Stage Dehumidifiers, Fans, Dryheat
4:00 AM
10:00 PM
18 HR
Load Drywall
4:00 AM
6:00 AM
2 HR
Hang, Tape, Sand, Fog Drywall
6:00 AM
9:00 PM
15 HR
Insulate crawlspace- Batts
8:00 AM
Noon
4 HR
Install New Water Meter
8:00 AM
10:00 AM
2 HR
Pour front entry porch
8:00 AM
10:00 AM
2 HR
Pick up Framing/ Drywall nailers/ Deadwood, Finish Cornice
8:00 AM
10:00 PM
14 HR
Master Bath Shower mud pan Install
9:00 AM
1:00 PM
4 HR
Habitat to remove extra drywall material
6:00 PM
9:00 PM
3 HR
Measure for closet systems
8:00: PM
10:00 PM
2 HR
Design Producer Paint Walk-Through
8:00 PM
9:00 PM
1 HR
Prime/Custom colors interior of house
9:00 PM
3:00 AM
6 HR
Stage Interior Stone Material
9:00 PM
10:00 PM
1 HR
Design Producer Tile Walk-Through
9:00 PM
10:00PM
1 HR
Load Tile into House
9:00 PM
10:00 PM
1 HR
Tile install
10:00 PM
8:00 AM
10 HR
Install Fireplace surround/hearth
10:00 PM
4:00 AM
6 HR
Install Interior Stone
10:00 PM
2:00 PM
16 HR
Stage Soffit Material
10:00 PM
11:00 PM
1 HR
Soffit install
11:00 PM
11:00 AM
12 HR
Stage Interior Trim
10:00 PM
11:00 PM
1 HR
Load Interior cabinets
11:00 PM
Midnight
1 HR
Trim-Door Install
11:00 PM
8:00 AM
9 HR
Day 5- Tuesday Oct 26th
A C T I V I T Y
Start Time
Finish Time
Duration
Cabinet Installation
Midnight
7:00 AM
7 HR
Measure for Countertops
3:00 AM
4:00 AM
1 HR
Courtyard, Porch, and Garage porch prep, form, and Pour
3:00 AM
8:00 AM
5 HR
Paint Prep- caulk/fill
4:00 AM
7:00 AM
3 HR
Stage Interior Paint
4:00 AM
5:00 AM
1 HR
Paint interior Walls & Trim
6:00 AM
Noon
6 HR
Install Countertops
7:00 AM
9:00 AM
2 HR
Measure for mirrors and shower glass
7:00 AM
8:00 AM
1 HR
Final grade fill material
8:00 AM
9:00 AM
1 HR
Final Grade
9:00 AM
Noon
3 HR
Back Splash install
9:00AM
12:00PM
3 HR
Start landscaping
Noon
2:00 PM
26 HR
Stage Wood floor
11:00 AM
Noon
1 HR
Install septic tank
Noon
4:00 PM
4 HR
Install irrigation
Noon
7:00 PM
7 HR
Install Wood floor & shoe mould
Noon
8:00 PM
8 HR
Stage All Kohler Bath Accessories in Bathrooms
2:30 PM
3:30 PM
1 HR
Design Producer Bath Accessories Walk-Through
3:30 PM
4:00 PM
.5 HR
Install Door Hardware & Finish Trim
4:00 PM
7:00 PM
3 HR
Bath & toilet accessories
4:00 PM
7:00 PM
3 HR
Designer Mirror Walk-Through
4:00PM
5:00PM
1 HR
Install Garage Doors/ openers
5:00 PM
8:00 PM
3 HR
Install Mirrors, Shower Enc.
5:00 PM
10:00 PM
5 HR
Design Producer Lighting Walk-Through
5:00 PM
6:00 PM
1 HR
Install Closet Systems
5:00 PM
10:00PM
5 HR
Security Finish
6:00 PM
8:00 PM
2 HR
Install Low Voltage Trim, Final
6:00 PM
9:00 PM
3 HR
Install HVAC Trim, Final/ A.C. Install
6:00 PM
1:00 AM
7 HR
Install Plumbing Fixtures, Final
6:00 PM
1:00 AM
7 HR
Install Electrical Trim, Final
6:00 PM
1:00 AM
7 HR
Install Wallpaper
10:00 PM
9:00 AM
9 HR
Paint Murals
10:00 PM
9:00 AM
9 HR
Day 6- Wednesday Oct 27th (Funiture Move-In/Key Hand Over Day)
A C T I V I T Y
Start Time
Finish Time
Duration
Blow-in ceiling insulation
5:00 AM
9:00 AM
4 HR
Stage Appliances
5:00 AM
6:00 AM
1 HR
Stage gutters and downspouts
6:00 AM
7:00AM
1 HR
Install river rock for "dry creek"
6:00 AM
9:00 AM
3 HR
Low voltage Landscape Lighting
6:00 AM
Noon
6 HR
Annuals & Planters
6:00 AM
9:00 AM
3 HR
Mulch
6:00 AM
10:00 AM
4 HR
Install Appliances
6:00 AM
10:00 AM
4 HR
Install fencing
6:00 AM
Noon
6 HR
Final Drywall Touch Up
6:00 AM
10:00 AM
4 HR
Final Paint touchup Int/Ext
6:00 AM
11:00 AM
5 HR
Final Grade Clean up & Spread Black Dirt
6:00 AM
8:00 AM
2 HR
Tile T/U
6:00 AM
9:00 AM
3 HR
Flooring T/U
6:00 AM
9:00 AM
3 HR
Sod
6:00 AM
11:00 AM
5 HR
Trim work T/U
6:00 AM
10:00 AM
4 HR
Install gutters and downspouts
7:00 AM
11:00AM
1 HR
Final Clean / Clean Windows
8:00 AM
2:00 PM
6 HR
Final inspection
10:00 AM
11:00 AM
1 HR
Street Sweep
11:00 AM
1:00 PM
2 HR
Restricted Access
Noon
Punch List Items
Noon
Key turn over to Extreme!
2:00PM
Designer Move-in
2:00 PM
2:00 PM
24 HR
Furniture Move-in
2:00 PM
4:00 PM
2 HR
Punch out and picture install
7:00 PM
Midnight
5 HR
Electrical Design fixture install
7:00 PM
11:00 PM
4 HR
Cable Final install
7:00 PM
9:00 PM
2 HR
Plasma TV install
7:00 PM
11:00 PM
4 HR
Install Blinds
7:00 PM
11:00 PM
4 HR
Clean site/Staging
7:00PM
7:00AM
12 HR
Day 7- Thursday Oct 28th (Reveal Day)
A C T I V I T Y
Start Time
Finish Time
Duration
5 Painters
6:00 AM
1:00 PM
7 HR
6 Trim carpenters
7:00 AM
11:00 AM
5 HR
Move materials and clean site
8:00 AM
1:00 PM
5 HR
Fire Company for watering Lawn
8:00 AM
9:00 AM
1 HR
Final Glass cleaning
8:00 AM
11:00 AM
3 HR
Final / Final Clean
8:00 AM
2:00 PM
6 HR
2 Electricians
8:00 AM
1:00 PM
5 HR
2 Landscapers
8:00 AM
1:00 PM
5 HR
2 HVAC Techs
8:00 AM
1:00 PM
5 HR
2 Plumbers
8:00 AM
1:00 PM
5 HR
Street Sweep
8:00 AM
9:00 AM
1 HR
Clean Exterior Windows
9:00 AM
Noon
3 HR
Move that bus!
2:00 PM
Day 8- Friday Oct 29th (Wrap Day / Clean-Up Day)
A C T I V I T Y
Start Time
Finish Time
Duration
Clear materials from staging
9:00 AM
6:00 PM
9 HR
Initial Equipment Pickup
9:00AM
11:00 AM
2 HR
Extra Materials to Habitat
9:00 AM
6:00 PM
9 HR
Press Conference
10:30 AM
12:30 PM
2 HR
Make Punch list
3:00 PM
6:00 PM
3 HR
Punch work
5:00 PM
8:00 PM
3 HR
Day 9- Saturday Oct 30th (Clean-Up / Punch Out Day)
A C T I V I T Y
Start Time
Finish Time
Duration
Clean up day
9:00 AM
4:00 PM
7 HR
Punch work
9:00 AM
4:00 PM
7 HR
Clear materials from staging
9:00 AM
4:00 PM
7 HR
Final Equipment Pickup
9:00 AM